CAPM Practice Test 2: This test features 50 multiple-choice questions designed to assess your understanding of both Predictive, Plan-Based Project Management and Agile Frameworks/Methodologies. These two approaches represent distinct philosophies in project execution, and mastering both is essential for success on the exam and in the real world. This practice test helps you evaluate your grasp of traditional project planning as well as adaptive, iterative delivery models.
CAPM Practice Test 2
CAPM Practice Test 2
Quiz-summary
0 of 50 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
Information
CAPM Practice Test 2
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 50 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- CAPM 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- Answered
- Review
-
Question 1 of 50
1. Question
When the dimensions of the dug canals for the new dam project were compared to the plan, a significant variance was discovered. As a result, the project manager had to hold a meeting with the team to decide on the next steps. To which of the following process groups does the project manager’s activity belong?
Correct
Reviewing the project performance in comparison to plans is part of the monitoring and controlling process group. These processes are meant for tracking, adjusting, and reporting on the project performance, as well as implementing corrective actions when needed to ensure the project is on track, budget and time-wise. Inspecting is not a process group, it’s rather a risk identification activity.
Incorrect
Reviewing the project performance in comparison to plans is part of the monitoring and controlling process group. These processes are meant for tracking, adjusting, and reporting on the project performance, as well as implementing corrective actions when needed to ensure the project is on track, budget and time-wise. Inspecting is not a process group, it’s rather a risk identification activity.
-
Question 2 of 50
2. Question
After creating the network diagram, the project manager identified three critical paths. What should the project manager do next?
Correct
The project manager should approve the network diagram and closely monitor all three critical paths. Theoretically, there is no limit on how many critical paths a network diagram could have. If a project has more than one critical path, then all critical paths must have exactly the same length.
Incorrect
The project manager should approve the network diagram and closely monitor all three critical paths. Theoretically, there is no limit on how many critical paths a network diagram could have. If a project has more than one critical path, then all critical paths must have exactly the same length.
-
Question 3 of 50
3. Question
Which technique is used to develop the WBS?
Correct
Scope decomposition is a planning method used to decompose and subdivide the project and scope deliverables into more manageable, small work units. The decomposition level depends on the complexity and size of the project
Incorrect
Scope decomposition is a planning method used to decompose and subdivide the project and scope deliverables into more manageable, small work units. The decomposition level depends on the complexity and size of the project
-
Question 4 of 50
4. Question
During a project status meeting, the project manager updated the sponsor on the project performance, indicating that the SPI is 0.75 and the CPI is 1.05. What does this imply?
Correct
A Schedule Performance Index (SPI) of less than 1 indicates that the project is behind schedule. A Cost Performance Index (CPI) greater than 1 means that the project is within the predetermined budget.
Incorrect
A Schedule Performance Index (SPI) of less than 1 indicates that the project is behind schedule. A Cost Performance Index (CPI) greater than 1 means that the project is within the predetermined budget.
-
Question 5 of 50
5. Question
A Business Analyst is assigned to a Mobile App development project. One week prior to the product delivery date, the client requests a change to a specific business requirement. What should the Business Analyst do?
Correct
Change requests should be reviewed and discussed by the Change Control Board (CCB) to analyze their impact on the project, including its delivery date, and accordingly, get accepted or rejected. The Business Analyst (BA) should not proceed with implementing the change without presenting the request to the CCB and getting their approval first.
Incorrect
Change requests should be reviewed and discussed by the Change Control Board (CCB) to analyze their impact on the project, including its delivery date, and accordingly, get accepted or rejected. The Business Analyst (BA) should not proceed with implementing the change without presenting the request to the CCB and getting their approval first.
-
Question 6 of 50
6. Question
During a project performance review meeting, a project manager presented the following figures: AC = $4,000, PV = $5,000, and EV = $5,500. What does that indicate about the project?
Correct
CV = EV – AC = $5,500 – $4,000 = $1,500. The Cost Variance (CV) is positive, which means that the project is under budget.
SV = EV – PV = $5,500 – $5,000 = $500. The Schedule Variance (SV) is positive, which means that the project is ahead of schedule.
Incorrect
CV = EV – AC = $5,500 – $4,000 = $1,500. The Cost Variance (CV) is positive, which means that the project is under budget.
SV = EV – PV = $5,500 – $5,000 = $500. The Schedule Variance (SV) is positive, which means that the project is ahead of schedule.
-
Question 7 of 50
7. Question
The longest path in a network diagram is known as:
Correct
In a network diagram, the critical path is the path with the longest series of tasks (PMBOK 7th edition, page 238).
Earned Value refers to the value of the work accomplished to date (PMBOK 7th edition, page 239). If the project gets terminated at this point, Earned Value will show you the value that the project has produced. In this case, the project’s Earned Value (EV) is $40,000 = 40% of the value of total work. The amount of $60,000 represents the Actual Cost (AC). The planned value is $50,000 (50% of the budget), while the cost variance is -$20,000 (EV – AC).
Incorrect
In a network diagram, the critical path is the path with the longest series of tasks (PMBOK 7th edition, page 238).
Earned Value refers to the value of the work accomplished to date (PMBOK 7th edition, page 239). If the project gets terminated at this point, Earned Value will show you the value that the project has produced. In this case, the project’s Earned Value (EV) is $40,000 = 40% of the value of total work. The amount of $60,000 represents the Actual Cost (AC). The planned value is $50,000 (50% of the budget), while the cost variance is -$20,000 (EV – AC).
-
Question 8 of 50
8. Question
A project manager is assigned to a 12-month project that has a $100,000 budget. Six months have passed and $60,000 has been spent. On closer inspection, the project manager finds out that so far, only 40% of the work has been completed. The value of the completed 40% work is referred to as:
Correct
Earned Value refers to the value of the work accomplished to date (PMBOK 7th edition, page 239). If the project gets terminated at this point, Earned Value will show you the value that the project has produced. In this case, the project’s Earned Value (EV) is $40,000 = 40% of the value of total work.
Incorrect
Earned Value refers to the value of the work accomplished to date (PMBOK 7th edition, page 239). If the project gets terminated at this point, Earned Value will show you the value that the project has produced. In this case, the project’s Earned Value (EV) is $40,000 = 40% of the value of total work.
-
Question 9 of 50
9. Question
Which of the following statements are true about the deliverables of a predictive project? (Select two)
Correct
Project deliverables can be products, services, or any other type of outcome. Acceptance criteria should be described and agreed upon.
Option A: In a predictive approach, project deliverables should be determined, described, and agreed upon as early as possible in the project, to avoid any costly changes later on.
Option C: The change is possible and should follow the change request process.
Option E: Project deliverables should be approved by the customer, not the project manager, in order to close the project.
Incorrect
Project deliverables can be products, services, or any other type of outcome. Acceptance criteria should be described and agreed upon.
Option A: In a predictive approach, project deliverables should be determined, described, and agreed upon as early as possible in the project, to avoid any costly changes later on.
Option C: The change is possible and should follow the change request process.
Option E: Project deliverables should be approved by the customer, not the project manager, in order to close the project.
-
Question 10 of 50
10. Question
Which of the following statements describes the characteristics of the predictive project management approach? (Select two)
Correct
Predictive methods focus on thoroughly analyzing and planning the future while taking into account known risks. The scope, time, and cost are all predetermined early in the project life cycle. Predictive teams often establish a Change Control Board (CCB) to ensure that only valuable changes are considered for implementation.
Incorrect
Predictive methods focus on thoroughly analyzing and planning the future while taking into account known risks. The scope, time, and cost are all predetermined early in the project life cycle. Predictive teams often establish a Change Control Board (CCB) to ensure that only valuable changes are considered for implementation.
-
Question 11 of 50
11. Question
In the predictive approach, which of the following terms is used for both schedule and cost to define what you’ll measure against later in the monitoring and controlling phase?
Correct
Cost and schedule baselines are used to assess performance in the monitoring and controlling phases.
Incorrect
Cost and schedule baselines are used to assess performance in the monitoring and controlling phases.
-
Question 12 of 50
12. Question
The diagram below depicts the decomposition of project deliverables into smaller tasks. This diagram is referred to as:
Correct
The WBS is a hierarchical decomposition of the total scope of work to create the required deliverables (PMBOK 7th edition, page 81). The planned work is included in the lowest level of the WBS components, which are called work packages.
Incorrect
The WBS is a hierarchical decomposition of the total scope of work to create the required deliverables (PMBOK 7th edition, page 81). The planned work is included in the lowest level of the WBS components, which are called work packages.
-
Question 13 of 50
13. Question
The project SPI is 0.8, while the CPI is 1.1. What should be the project manager’s main concern?
Correct
Since the Schedule Performance Index (SPI) is less than 1.0, then the project is behind schedule. Consequently, the project manager should be concerned about the project schedule.
Option B: Since CPI is 1.1, then the project is under budget. Thus, the project is on track cost-wise.
Option D: There is no indication in the question that the project manager should be concerned about risks.
Incorrect
Since the Schedule Performance Index (SPI) is less than 1.0, then the project is behind schedule. Consequently, the project manager should be concerned about the project schedule.
Option B: Since CPI is 1.1, then the project is under budget. Thus, the project is on track cost-wise.
Option D: There is no indication in the question that the project manager should be concerned about risks.
-
Question 14 of 50
14. Question
What should the project manager do to prevent scope creep and focus on fulfilling product requirements?
Correct
The project manager can avoid scope creep by adhering to the agreed-upon change management process. Change management processes have to be set up front and should be very straightforward. Essentially, when a change is suggested, it should be reviewed, approved, or rejected, and then incorporated into the project plan if it’s approved (PMBOK 7th edition, page 87).
Incorrect
The project manager can avoid scope creep by adhering to the agreed-upon change management process. Change management processes have to be set up front and should be very straightforward. Essentially, when a change is suggested, it should be reviewed, approved, or rejected, and then incorporated into the project plan if it’s approved (PMBOK 7th edition, page 87).
-
Question 15 of 50
15. Question
A project manager is overseeing a project that has recently experienced inconsistent performance and a high defect rate. During a meeting, the sponsor asks where the project is currently standing, requesting an overview of work performance. Which of the following documents should the project manager send to the sponsor?
Correct
The status report is a work performance report that includes information on the project’s progress and status (PMBOK 7th edition, page 190). The sponsor asked for work performance information to help them gain insight into the project situation and make better decisions. A status report can include information about Earned Value (EV), trend lines and forecasts, reserve burndown charts, defect and risk summaries, etc.
Options A & C: Even though the project is at high risk and is encountering quality issues, the sponsor didn’t explicitly request a detailed risk or quality report.
Option D: The project management plan is not a reporting document; it’s a planning document that is elaborated in the project planning phase.
Incorrect
The status report is a work performance report that includes information on the project’s progress and status (PMBOK 7th edition, page 190). The sponsor asked for work performance information to help them gain insight into the project situation and make better decisions. A status report can include information about Earned Value (EV), trend lines and forecasts, reserve burndown charts, defect and risk summaries, etc.
Options A & C: Even though the project is at high risk and is encountering quality issues, the sponsor didn’t explicitly request a detailed risk or quality report.
Option D: The project management plan is not a reporting document; it’s a planning document that is elaborated in the project planning phase.
-
Question 16 of 50
16. Question
What is Earned Value?
Correct
Earned Value (EV) is the method used to measure how much of the allocated budget should have been spent in view of the work realized to date (PMBOK 7th edition, page 239). This technique allows the project manager to calculate the Cost Variance (CV), which is the difference between the budgeted cost of the performed work (EV) and its actual cost, to eventually find out whether the project is under or over budget. The amount of money that has been spent so far represents the Actual Cost (AC).
Incorrect
Earned Value (EV) is the method used to measure how much of the allocated budget should have been spent in view of the work realized to date (PMBOK 7th edition, page 239). This technique allows the project manager to calculate the Cost Variance (CV), which is the difference between the budgeted cost of the performed work (EV) and its actual cost, to eventually find out whether the project is under or over budget. The amount of money that has been spent so far represents the Actual Cost (AC).
-
Question 17 of 50
17. Question
What could be considered as the foundation for identifying current or future issues to support the decision of change requests?
Correct
Work Performance Information includes data on project performance (e.g., status of deliverables, schedule, costs), which can help identify current or future issues by comparing actual performance against the baseline.
Incorrect
Work Performance Information includes data on project performance (e.g., status of deliverables, schedule, costs), which can help identify current or future issues by comparing actual performance against the baseline.
-
Question 18 of 50
18. Question
Which tool or technique is used to validate the scope of a project?
Correct
Inspection is the technique used to validate the scope by measuring, examining, and testing deliverables to ensure they meet the defined criteria.
Incorrect
Inspection is the technique used to validate the scope by measuring, examining, and testing deliverables to ensure they meet the defined criteria.
-
Question 19 of 50
19. Question
Subdividing project deliverables and project work into smaller, more manageable parts is related to:
Correct
Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable parts.
Incorrect
Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable parts.
-
Question 20 of 50
20. Question
A stakeholder expresses a need that was unknown to the project manager. Which stakeholder management process did the project manager likely skip?
Correct
The project manager likely missed a step in the Identify Stakeholders process, as this process involves determining who the stakeholders are and what their needs might be.
Incorrect
The project manager likely missed a step in the Identify Stakeholders process, as this process involves determining who the stakeholders are and what their needs might be.
-
Question 21 of 50
21. Question
An activity has an Early Start (ES) of day 5, a Late Start (LS) of day 12, an Early Finish (EF) of day 10, and a Late Finish (LF) of day 17. Which of the following statements are correct regarding this activity? (Select two)
Correct
Since it has a 7-day float, this activity is not on the critical path. The float of this activity can be calculated by subtracting the Early Start (day 5) from the Late Start (day 12) or by subtracting the Early Finish (day 10) from the Late Finish (day 17). Since the float of the activity is greater than zero, then it’s not on the critical path. Remember that critical path activities have zero float.
Option D: Lag time is the amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity. However, since the described scenario doesn’t have any information about the successor activity, it does not consist of a lag.
Incorrect
Since it has a 7-day float, this activity is not on the critical path. The float of this activity can be calculated by subtracting the Early Start (day 5) from the Late Start (day 12) or by subtracting the Early Finish (day 10) from the Late Finish (day 17). Since the float of the activity is greater than zero, then it’s not on the critical path. Remember that critical path activities have zero float.
Option D: Lag time is the amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity. However, since the described scenario doesn’t have any information about the successor activity, it does not consist of a lag.
-
Question 22 of 50
22. Question
Which process is conducted from the start to the finish of the project and is ultimately the responsibility of the project manager?
Correct
Control Project Work is conducted from the start to the finish of the project and is the project manager’s responsibility.
Incorrect
Control Project Work is conducted from the start to the finish of the project and is the project manager’s responsibility.
-
Question 23 of 50
23. Question
During which process does a project manager confirm resource availability and obtain the team necessary to complete project activities?
Correct
Acquire Resources is the process where the project manager confirms resource availability and obtains the team necessary to complete project activities.
Incorrect
Acquire Resources is the process where the project manager confirms resource availability and obtains the team necessary to complete project activities.
-
Question 24 of 50
24. Question
What performance measurement is used to assess the magnitude of variance in a project?
Correct
Variance Analysis is used to assess the magnitude of variance in a project by comparing planned and actual performance.
Incorrect
Variance Analysis is used to assess the magnitude of variance in a project by comparing planned and actual performance.
-
Question 25 of 50
25. Question
A project manager calculates the early & late start and finish dates of a new project activity. One of the activities has the following representation. What is this activity’s float?
Correct
Float, Total float, Slack, or activity float represents how long an activity can be delayed without causing a delay in the project completion date. On a critical path, the total float is zero. You can calculate an activity float by subtracting the Early Start date of the activity from its Late Start date: (12 – 4 = 8 days), or by subtracting the Early Finish date of the activity from its Late Finish date (28 – 20 = 8 days).
Incorrect
Float, Total float, Slack, or activity float represents how long an activity can be delayed without causing a delay in the project completion date. On a critical path, the total float is zero. You can calculate an activity float by subtracting the Early Start date of the activity from its Late Start date: (12 – 4 = 8 days), or by subtracting the Early Finish date of the activity from its Late Finish date (28 – 20 = 8 days).
-
Question 26 of 50
26. Question
The Agile triangle of constraints is different from the traditional triangle because it allows:
Correct
Unlike predictive approaches, projects that follow adaptive approaches have fixed resources and schedules and flexible scope. While the scope might change in agile projects, teams commit to fixed work iterations known as sprints, when implementing a scrum framework.
Incorrect
Unlike predictive approaches, projects that follow adaptive approaches have fixed resources and schedules and flexible scope. While the scope might change in agile projects, teams commit to fixed work iterations known as sprints, when implementing a scrum framework.
-
Question 27 of 50
27. Question
An organization has decided to adopt the agile approach for its new project. What should they expect to get at the conclusion of the first sprint?
Correct
Agile uses iterations, also known as sprints, in each, a potentially shippable increment of the product is produced (Agile Practice Guide, page 101).
Incorrect
Agile uses iterations, also known as sprints, in each, a potentially shippable increment of the product is produced (Agile Practice Guide, page 101).
-
Question 28 of 50
28. Question
In projects following the Scrum framework, which of the following questions won’t be asked to team members during daily stand-ups?
Correct
In contrast with flow-based Agile which focuses on the team’s throughput, iteration-based Agile focuses on accountability through three standard questions:
What was completed yesterday?
What will be completed today?
Are there any blockers or impediments?
Incorrect
In contrast with flow-based Agile which focuses on the team’s throughput, iteration-based Agile focuses on accountability through three standard questions:
What was completed yesterday?
What will be completed today?
Are there any blockers or impediments?
-
Question 29 of 50
29. Question
The product owner and the project team are currently preparing and updating user stories for the next iterations. What activity does this depict?
Correct
Backlog refinement involves preparing the next iteration’s stories. In order to make sure the backlog contains the right items for the next iteration, the project manager, along with the team, should review and prioritize backlog items, ensuring that top items are ready to be delivered (PMBOK 7th edition, page 235). This activity can take place as a formal planned meeting or as a regular ongoing task.
Incorrect
Backlog refinement involves preparing the next iteration’s stories. In order to make sure the backlog contains the right items for the next iteration, the project manager, along with the team, should review and prioritize backlog items, ensuring that top items are ready to be delivered (PMBOK 7th edition, page 235). This activity can take place as a formal planned meeting or as a regular ongoing task.
-
Question 30 of 50
30. Question
A project manager is facilitating a meeting with his project team and key stakeholders to prioritize all product backlog items based on their business value and risk level. Where should each category of items be placed in the product backlog? (from top to bottom)
Correct
Items of high priority and high risk should be on top as completing them sooner generates more new knowledge, which eliminates uncertainty and reduces risk. Items of high value and low risk should be tackled next. These items are great for achieving quick wins. The project team can then consider working on low-value and low-risk items. Finally, items of low value and high risk should be put off and placed at the bottom of the product backlog since they are not worth the effort. To sum up, the right order is: A, B, D, and then C from top to bottom.
Incorrect
Items of high priority and high risk should be on top as completing them sooner generates more new knowledge, which eliminates uncertainty and reduces risk. Items of high value and low risk should be tackled next. These items are great for achieving quick wins. The project team can then consider working on low-value and low-risk items. Finally, items of low value and high risk should be put off and placed at the bottom of the product backlog since they are not worth the effort. To sum up, the right order is: A, B, D, and then C from top to bottom.
-
Question 31 of 50
31. Question
In an Agile project, how many members a project team should include?
Correct
It’s recommended that an agile team should include 3 to 9 members. Since the level of communication deteriorates as the team size increases, Agile organizations favor smaller teams. For instance, it’s better to have two teams of five people than one team of ten.
Incorrect
It’s recommended that an agile team should include 3 to 9 members. Since the level of communication deteriorates as the team size increases, Agile organizations favor smaller teams. For instance, it’s better to have two teams of five people than one team of ten.
-
Question 32 of 50
32. Question
A project manager is choosing a development approach for a new project. Which of the following reasons would motivate the project manager to opt for an adaptive approach instead of a predictive one?
Correct
Unlike the predictive approach which requires change requests to go through the organization’s change control process, the adaptive approach welcomes changes and uses them for frequent planning. During each iteration, the team focuses on producing a subset of the product’s features, while continuously refining and reprioritizing the product backlog items to meet new or modified requirements.
Options C & D: Change requests are not automatically approved; instead, they are discussed with the product owner first, and then they get prioritized in subsequent iterations as per their recommendations.
Incorrect
Unlike the predictive approach which requires change requests to go through the organization’s change control process, the adaptive approach welcomes changes and uses them for frequent planning. During each iteration, the team focuses on producing a subset of the product’s features, while continuously refining and reprioritizing the product backlog items to meet new or modified requirements.
Options C & D: Change requests are not automatically approved; instead, they are discussed with the product owner first, and then they get prioritized in subsequent iterations as per their recommendations.
-
Question 33 of 50
33. Question
Which of the following topics can be discussed in a retrospective meeting?
Correct
During the sprint retrospective, the project manager should identify what went well during the sprint and what can be done differently in the next sprint. A possible topic is the timing of the standup. If team members are showing dissatisfaction with the current schedule, then the retrospective meeting is the right event to discuss the issue.
Option A & B: The sprint planning meeting is the right meeting for discussing which tasks should be prioritized in the next sprint and how to decompose user stories into manageable tasks.
Option C: Dedicated project team meetings and Backlog refinement meetings should address topics related to the product development, including finding ways on how to fix the regressions.
Incorrect
During the sprint retrospective, the project manager should identify what went well during the sprint and what can be done differently in the next sprint. A possible topic is the timing of the standup. If team members are showing dissatisfaction with the current schedule, then the retrospective meeting is the right event to discuss the issue.
Option A & B: The sprint planning meeting is the right meeting for discussing which tasks should be prioritized in the next sprint and how to decompose user stories into manageable tasks.
Option C: Dedicated project team meetings and Backlog refinement meetings should address topics related to the product development, including finding ways on how to fix the regressions.
-
Question 34 of 50
34. Question
In an agile development approach, what does a cross-functional team mean?
Correct
A cross-functional team must possess the necessary competencies for creating a product or a service independently, without relying on other members outside of the team.
Option A: A self-organizing team is when individuals collectively determine the best way to accomplish the sprint goal.
Incorrect
A cross-functional team must possess the necessary competencies for creating a product or a service independently, without relying on other members outside of the team.
Option A: A self-organizing team is when individuals collectively determine the best way to accomplish the sprint goal.
-
Question 35 of 50
35. Question
During a sprint planning, a team member noticed that artifacts are missing, and the project manager asked the member to resolve the issue. What should the team member add? (Select two)
Correct
An increment is a validated and approved deliverable produced at the end of each sprint, reflecting a functional and usable subset of the project’s overall capabilities. It represents a tangible portion of the project’s performance that meets the definition of done and can be integrated into the existing product or system. A sprint backlog is a list of tasks selected from the Product Backlog for a specific sprint in Scrum. It represents a subset of work for short-term focus rather than the entire project scope.
Incorrect
An increment is a validated and approved deliverable produced at the end of each sprint, reflecting a functional and usable subset of the project’s overall capabilities. It represents a tangible portion of the project’s performance that meets the definition of done and can be integrated into the existing product or system. A sprint backlog is a list of tasks selected from the Product Backlog for a specific sprint in Scrum. It represents a subset of work for short-term focus rather than the entire project scope.
-
Question 36 of 50
36. Question
One of the team members asks the project manager when a Sprint is considered completed. What should be the project manager’s response?
Correct
A sprint is considered complete only when it reaches the end of its duration/timebox, which is usually 1 to 4 weeks. In some cases, the sprint ends without finishing all of the assigned tasks, so this can’t be the criteria for sprint completion.
Incorrect
A sprint is considered complete only when it reaches the end of its duration/timebox, which is usually 1 to 4 weeks. In some cases, the sprint ends without finishing all of the assigned tasks, so this can’t be the criteria for sprint completion.
-
Question 37 of 50
37. Question
Using an Agile approach, where should product requirements be documented?
Correct
Product requirements are documented under the backlog as user stories. The backlog user stories are then continuously prioritized and refined. The WBS is only used in the predictive approach.
Incorrect
Product requirements are documented under the backlog as user stories. The backlog user stories are then continuously prioritized and refined. The WBS is only used in the predictive approach.
-
Question 38 of 50
38. Question
Typically, an agile scrum sprint is ____________ long.
Correct
A Sprint has to be long enough for the team to finish all included stories. As per a Scrum rule, a Sprint should never exceed one month. The duration of a sprint depends on the project size and complexity as well as the team’s capacities. It takes 2 to 4 weeks on average to complete a sprint with a team of 3-9 members working on a single project.
Incorrect
A Sprint has to be long enough for the team to finish all included stories. As per a Scrum rule, a Sprint should never exceed one month. The duration of a sprint depends on the project size and complexity as well as the team’s capacities. It takes 2 to 4 weeks on average to complete a sprint with a team of 3-9 members working on a single project.
-
Question 39 of 50
39. Question
A cross-functional team should always make sure to focus on:
Correct
Delivering value should always be the agile team’s top priority as it represents one of the agile manifesto principles: “working software over comprehensive documentation”. From the client’s perspective, value represents the benefit derived from using a product or a service.
Incorrect
Delivering value should always be the agile team’s top priority as it represents one of the agile manifesto principles: “working software over comprehensive documentation”. From the client’s perspective, value represents the benefit derived from using a product or a service.
-
Question 40 of 50
40. Question
What is the primary distinction between Agile and Scrum?
Correct
On the surface, Agile and Scrum look similar as they both rely on an iterative process, frequent client interaction, and collaborative decision-making. The primary distinction between Agile and Scrum is that Agile is a project management philosophy that utilizes a core set of values or principles, while Scrum is a specific Agile practice used to facilitate a project. Although Scrum is an approach within Agile, Agile does not necessarily imply Scrum since Agile encompasses a wide range of approaches. Scrum is based on a small set of core values, principles, and practices (collectively forming the Scrum framework).
Incorrect
On the surface, Agile and Scrum look similar as they both rely on an iterative process, frequent client interaction, and collaborative decision-making. The primary distinction between Agile and Scrum is that Agile is a project management philosophy that utilizes a core set of values or principles, while Scrum is a specific Agile practice used to facilitate a project. Although Scrum is an approach within Agile, Agile does not necessarily imply Scrum since Agile encompasses a wide range of approaches. Scrum is based on a small set of core values, principles, and practices (collectively forming the Scrum framework).
-
Question 41 of 50
41. Question
The role of the product owner in an Agile project is: (Select two)
Correct
The product owner represents the business, customer, or end-user as they’re regarded as the voice of the customer. The Product Owner is responsible for managing the product backlog by maximizing the value produced by the team and ensuring that the stories meet the user’s needs and comply with the Definition of Done (DoD) (PMBOK 7th edition, page 245).
Option A: The Agile team manages the sprint backlog.
Options B & E: The Agile project manager is responsible for supporting the team and removing impediments.
Incorrect
The product owner represents the business, customer, or end-user as they’re regarded as the voice of the customer. The Product Owner is responsible for managing the product backlog by maximizing the value produced by the team and ensuring that the stories meet the user’s needs and comply with the Definition of Done (DoD) (PMBOK 7th edition, page 245).
Option A: The Agile team manages the sprint backlog.
Options B & E: The Agile project manager is responsible for supporting the team and removing impediments.
-
Question 42 of 50
42. Question
A key stakeholder requested the project manager to urgently add a new user story to improve the product. How should the project manager respond to this request?
Correct
The project manager should add the user story to the product backlog and let the product owner decide its priority. When a new requirement is received, it should be added to the product backlog (not the sprint backlog) and then prioritized by the product owner in order to be implemented. It is the responsibility of the product owner to maintain and refine the product backlog. This being said, a request can be made by any stakeholder and a user story can be created by anyone involved in the project and not just the product owner.
Incorrect
The project manager should add the user story to the product backlog and let the product owner decide its priority. When a new requirement is received, it should be added to the product backlog (not the sprint backlog) and then prioritized by the product owner in order to be implemented. It is the responsibility of the product owner to maintain and refine the product backlog. This being said, a request can be made by any stakeholder and a user story can be created by anyone involved in the project and not just the product owner.
-
Question 43 of 50
43. Question
To gauge each team member’s stance on a particular decision, a project manager uses the Fist of five voting technique. When the team starts voting, one member raises five fingers. What does this mean?
Correct
The Fist of five or Fist to five is a voting technique that agile teams use to help them achieve consensus during decision-making meetings or sessions. This method is used as follows: The facilitator states the decision or action the team is going to vote on and then asks each one of the attendees to hold up a number of fingers that corresponds to their level of support for the stated decision. A closed fist signifies full objection, whereas five fingers mean full support for the decision. Until everyone holds up three or more fingers, the voting goes through multiple rounds to achieve consensus.
Incorrect
The Fist of five or Fist to five is a voting technique that agile teams use to help them achieve consensus during decision-making meetings or sessions. This method is used as follows: The facilitator states the decision or action the team is going to vote on and then asks each one of the attendees to hold up a number of fingers that corresponds to their level of support for the stated decision. A closed fist signifies full objection, whereas five fingers mean full support for the decision. Until everyone holds up three or more fingers, the voting goes through multiple rounds to achieve consensus.
-
Question 44 of 50
44. Question
In the graph below, what concepts or approaches correspond respectively to positions A, B, C, and D?
Correct
A. Lean: a set of concepts that includes eliminating waste, amplifying learning, and delivering as fast as possible.
B. Kanban: a subset of lean which also refers to a framework within agile.
C. Agile: a subset of lean and an umbrella for several frameworks.
D. Scrum: one of the agile frameworks.
Please note that in the real exam such a question usually comes in the form of “drag & drop”.
Incorrect
A. Lean: a set of concepts that includes eliminating waste, amplifying learning, and delivering as fast as possible.
B. Kanban: a subset of lean which also refers to a framework within agile.
C. Agile: a subset of lean and an umbrella for several frameworks.
D. Scrum: one of the agile frameworks.
Please note that in the real exam such a question usually comes in the form of “drag & drop”.
-
Question 45 of 50
45. Question
What is a key element of delivering value early in Agile projects?
Correct
Agile methodologies emphasize delivering small, working increments of a product frequently. This allows teams to obtain feedback, adapt, and make improvements while delivering value continuously.
Incorrect
Agile methodologies emphasize delivering small, working increments of a product frequently. This allows teams to obtain feedback, adapt, and make improvements while delivering value continuously.
-
Question 46 of 50
46. Question
What is a key factor that helps agile teams deliver at maximum speed?
Correct
Continuous integration involves the frequent incorporation of individual contributions into the overall project and retesting the entire product to ensure that the integration is successful.
Incorrect
Continuous integration involves the frequent incorporation of individual contributions into the overall project and retesting the entire product to ensure that the integration is successful.
-
Question 47 of 50
47. Question
How does scope management in adaptive projects impact the creation of WBS?
Correct
In agile projects, scope evolves continuously. Rather than creating a static Work Breakdown Structure (WBS) at the start, the scope is managed through the backlog, which is constantly refined.
Option B: Creating a detailed WBS at the start is typical in a predictive project. Agile projects, on the other hand, favor ongoing backlog refinement rather than upfront detailed scope management.
Option D: Agile projects focus on delivering increments of value throughout the project. Waiting until project closure to define scope contradicts Agile’s iterative delivery approach.
Incorrect
In agile projects, scope evolves continuously. Rather than creating a static Work Breakdown Structure (WBS) at the start, the scope is managed through the backlog, which is constantly refined.
Option B: Creating a detailed WBS at the start is typical in a predictive project. Agile projects, on the other hand, favor ongoing backlog refinement rather than upfront detailed scope management.
Option D: Agile projects focus on delivering increments of value throughout the project. Waiting until project closure to define scope contradicts Agile’s iterative delivery approach.
-
Question 48 of 50
48. Question
What is the key measure of progress in iteration-based agile?
Correct
In iteration-based agile, progress is measured primarily by the number of work items or features that are completed at the end of each iteration. This approach aligns with the Agile Manifesto’s principle that “working software is the primary measure of progress.”
Incorrect
In iteration-based agile, progress is measured primarily by the number of work items or features that are completed at the end of each iteration. This approach aligns with the Agile Manifesto’s principle that “working software is the primary measure of progress.”
-
Question 49 of 50
49. Question
How is work-in-progress managed differently in flow-based agile compared to iteration-based agile?
Correct
In flow-based agile, such as Kanban, teams manage work by limiting the number of tasks that can be in progress at any given time.
Incorrect
In flow-based agile, such as Kanban, teams manage work by limiting the number of tasks that can be in progress at any given time.
-
Question 50 of 50
50. Question
In which methodology does the team continuously work on the highest priority item, without the use of timeboxed iterations?
Correct
In Kanban, there are no fixed timeboxed iterations like in Scrum or XP. Teams continuously work on the highest priority items from a backlog, with a focus on limiting work in progress (WIP) and improving flow.
Incorrect
In Kanban, there are no fixed timeboxed iterations like in Scrum or XP. Teams continuously work on the highest priority items from a backlog, with a focus on limiting work in progress (WIP) and improving flow.
Great work on completing Practice Test 2. To continue your progress, Return to the CAPM Practice Test main page and try Mock Tests.
CAPM Practice Test Syllabus
This test is based on CAPM’s emphasis on hybrid project environments and includes questions from the following areas:
- Predictive, Plan-Based Methodologies (25 Questions)
- Project lifecycle phases (Initiation to Closing)
- Work Breakdown Structure (WBS), Gantt charts, and network diagrams
- Change control, scope baseline, earned value management (EVM)
- Heavy documentation and phase-gate reviews
- Stakeholder communication and risk response planning in predictive models
- Agile Frameworks & Methodologies (25 Questions)
- Agile values and principles (Agile Manifesto)
- Scrum roles (Product Owner, Scrum Master, Dev Team) and ceremonies
- Kanban and flow-based metrics (WIP limits, cycle time)
- User stories, product backlog, sprint planning and retrospectives
- Adaptive planning, continuous delivery, and customer collaboration
This mix ensures you’re equally tested on structured planning and flexible delivery practices.