This 50‑question practice test focuses on the Fundamentals & Core Concepts of Project Management along with Business Analysis Frameworks. These Practice exams are designed to mirror the real PMP exam’s difficulty, it will help you build confidence and identify areas for review before test day. Whether you’re new to project management or reinforcing your existing knowledge, this test is a great way to benchmark your readiness.
Since it is a practice test only, You have no tome limit to complete all 50 multiple‑choice questions. However, you are advised to complete the CAMP Practice test without taking much time. Select the best answer for each question, then click Finish Quiz at the end to see your score and detailed explanations. No negative marking answer every question.
CAPM Practice Test 1
This practice test features 50 multiple choice questions half focused on Project Management Fundamentals & Core Concepts, and half on Business Analysis Frameworks. Designed to mirror the real exam’s mix of theory and application, it will help you pinpoint strengths and gaps in both domains. Perfect for early stage review or a quick refresher before diving into deeper practice.
CAPM Practice Test 1
Quiz-summary
0 of 50 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
Information
Practice Test 1: Project Management Fundamentals & Core Concepts (%50) + Business Analysis Frameworks (%50)
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 50 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- CAPM 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- Answered
- Review
-
Question 1 of 50
1. Question
During product validation, a key stakeholder refused to sign off on the acceptance document, stating that certain functionalities did not meet their expectations. What could the project manager have done to prevent this situation?
Correct
Stakeholders need to get involved early on during project planning and sometimes during the project initiation as well. Key stakeholders should also be involved during the quality control phase so that they can assess the project deliverables and recommend any changes before the official acceptance. Since the concerned key stakeholder is responsible for signing off the acceptance document, their power is considered high. Therefore, stakeholders who are identified to have high power using the power/interest grid should be managed closely and kept satisfied throughout the whole project.
Incorrect
Stakeholders need to get involved early on during project planning and sometimes during the project initiation as well. Key stakeholders should also be involved during the quality control phase so that they can assess the project deliverables and recommend any changes before the official acceptance. Since the concerned key stakeholder is responsible for signing off the acceptance document, their power is considered high. Therefore, stakeholders who are identified to have high power using the power/interest grid should be managed closely and kept satisfied throughout the whole project.
-
Question 2 of 50
2. Question
Which of the following documents does the project manager need to develop the project charter? (Select three)
Correct
To develop the Project Charter, the project manager needs business documents such as the project’s business case, benefits/strategic plan, and agreements. The Project Management Plan and the Cost Management Plan are developed once the project charter is signed.
Incorrect
To develop the Project Charter, the project manager needs business documents such as the project’s business case, benefits/strategic plan, and agreements. The Project Management Plan and the Cost Management Plan are developed once the project charter is signed.
-
Question 3 of 50
3. Question
A project manager is leading a project that consists of four phases. Which meeting should the project manager hold at each phase to ensure the stakeholders’ continuous commitment?
Correct
Stage-gate or phase review meetings represent an opportunity for project stakeholders to review project progress along with planned future actions. In these meetings, project stakeholders can assess whether or not the project is on track to meet the organization’s expectations (PMBOK 7th edition, page 42). The project manager should schedule gate meetings at key milestones throughout the project to not only ensure it is on track but also demonstrate to the project stakeholders that the project is staying on course.
Incorrect
Stage-gate or phase review meetings represent an opportunity for project stakeholders to review project progress along with planned future actions. In these meetings, project stakeholders can assess whether or not the project is on track to meet the organization’s expectations (PMBOK 7th edition, page 42). The project manager should schedule gate meetings at key milestones throughout the project to not only ensure it is on track but also demonstrate to the project stakeholders that the project is staying on course.
-
Question 4 of 50
4. Question
While overseeing the execution of an industrial project, a project manager observes that two stakeholders are frequently in disagreement, potentially affecting the project negatively. Which of the following options should be used to record and track this type of situation?
Correct
The issue log, also called an issue register, is a project document that records and tracks all issues that have a negative impact on the project (PMBOK 7th edition, page 185). Once created, it’ll be the project manager’s tool to monitor and communicate all that is going on in the project. Such issues may involve resources leaving the project, conflicting teams, or even individuals with low morale.
Options A & B: Problem log and dispute log are both made-up terms.
Option C: A change log is used to document all change requests.
Incorrect
The issue log, also called an issue register, is a project document that records and tracks all issues that have a negative impact on the project (PMBOK 7th edition, page 185). Once created, it’ll be the project manager’s tool to monitor and communicate all that is going on in the project. Such issues may involve resources leaving the project, conflicting teams, or even individuals with low morale.
Options A & B: Problem log and dispute log are both made-up terms.
Option C: A change log is used to document all change requests.
-
Question 5 of 50
5. Question
Activities that involve ongoing, routine tasks designed to maintain and support the organization’s infrastructure and processes are most likely referred to as ________.
Correct
Operations involve routine, ongoing activities that maintain and support the day-to-day functioning of an organization’s infrastructure and processes.
Incorrect
Operations involve routine, ongoing activities that maintain and support the day-to-day functioning of an organization’s infrastructure and processes.
-
Question 6 of 50
6. Question
A project team is reluctant to begin work on a project because key stakeholders may request proper authorization and clearly defined objectives before proceeding. What should the project manager do?
Correct
A project charter is an official document created by the project initiator or sponsor that formally authorizes the project’s initiation. It grants the project manager the authority to allocate organizational resources and undertake project activities.
Option D: While identifying risks and updating the risk register is important, the project cannot start without getting authorized.
Incorrect
A project charter is an official document created by the project initiator or sponsor that formally authorizes the project’s initiation. It grants the project manager the authority to allocate organizational resources and undertake project activities.
Option D: While identifying risks and updating the risk register is important, the project cannot start without getting authorized.
-
Question 7 of 50
7. Question
Upon delivering a rebranding project, the sponsor, as well as other key stakeholders, are hesitant to accept deliverables and close the project. What should the project manager do? (Select three)
Correct
The project manager should not close the project when key stakeholders are not satisfied. They should try to discuss, identify, and resolve any issues or misunderstandings first.
Incorrect
The project manager should not close the project when key stakeholders are not satisfied. They should try to discuss, identify, and resolve any issues or misunderstandings first.
-
Question 8 of 50
8. Question
All of the following statements are true, except:
Correct
Programs are not big projects. While a program mainly focuses on maximizing the organization’s profits, project management targets the creation of deliverables that meet and satisfy stakeholder needs.
Incorrect
Programs are not big projects. While a program mainly focuses on maximizing the organization’s profits, project management targets the creation of deliverables that meet and satisfy stakeholder needs.
-
Question 9 of 50
9. Question
Which interpersonal skills does a project manager use frequently in a project? (Select three answers)
Correct
Interpersonal skills that are used frequently in projects include emotional intelligence, decision-making, and conflict resolution. These are the skills used to establish and maintain relationships with others (PMBOK 7th edition, page 24). Emotional intelligence is the ability to recognize, understand, manage, and effectively be aware of the emotions of oneself and others. Throughout the project, daily decisions are made, therefore a project manager should exhibit the right choice of decision-making technique and approach. Moreover, Conflict management is crucial as it’s the ability to handle and resolve conflicts within a project team.
Incorrect
Interpersonal skills that are used frequently in projects include emotional intelligence, decision-making, and conflict resolution. These are the skills used to establish and maintain relationships with others (PMBOK 7th edition, page 24). Emotional intelligence is the ability to recognize, understand, manage, and effectively be aware of the emotions of oneself and others. Throughout the project, daily decisions are made, therefore a project manager should exhibit the right choice of decision-making technique and approach. Moreover, Conflict management is crucial as it’s the ability to handle and resolve conflicts within a project team.
-
Question 10 of 50
10. Question
A project manager is working on a contract. After completing the contract and closing the project, she finds herself without work. What type of organizational structure does the project manager work in?
Correct
A Project-oriented organization, or a projectized organization, is one in which a considerable part of its processes and activities take place in the form of projects. There is no defined hierarchy; resources are brought together specifically for the purpose of a project. Once the project is finished, they’re either moved to a new project or released.
Incorrect
A Project-oriented organization, or a projectized organization, is one in which a considerable part of its processes and activities take place in the form of projects. There is no defined hierarchy; resources are brought together specifically for the purpose of a project. Once the project is finished, they’re either moved to a new project or released.
-
Question 11 of 50
11. Question
You are managing six projects at the same time within the company. Two projects are of a similar type, while the other four are completely different. You work as a ______________.
Correct
In portfolio management, a group of related or non-related programs and projects are managed in coordination (PMBOK 7th edition, page 244). Portfolio management is intended to reduce the gap between strategy and implementation by aligning projects to attain business objectives.
Incorrect
In portfolio management, a group of related or non-related programs and projects are managed in coordination (PMBOK 7th edition, page 244). Portfolio management is intended to reduce the gap between strategy and implementation by aligning projects to attain business objectives.
-
Question 12 of 50
12. Question
During the kick-off meeting of their first project, the project manager presents the project plan to stakeholders. As they go through the details, a stakeholder expressed frustration with the plan’s inaccuracies in reflecting their expectations. What is the most likely reason behind the project manager’s inaccurate description of stakeholder requirements?
Correct
The project manager most likely failed to engage stakeholders adequately, leading to poorly defined requirements and dissatisfaction. Effective stakeholder engagement is needed for identifying needs and aligning the project scope with expectations.
Incorrect
The project manager most likely failed to engage stakeholders adequately, leading to poorly defined requirements and dissatisfaction. Effective stakeholder engagement is needed for identifying needs and aligning the project scope with expectations.
-
Question 13 of 50
13. Question
A project involves numerous stakeholders due to its multiple phases and various tasks to execute. What should the project manager do?
Correct
You should identify all project stakeholders, regardless of their number, and then analyze each one of them in order to prioritize the engagement (The PMBOK Guide 7th Edition, page 12).
Incorrect
You should identify all project stakeholders, regardless of their number, and then analyze each one of them in order to prioritize the engagement (The PMBOK Guide 7th Edition, page 12).
-
Question 14 of 50
14. Question
During the planning phase, the project manager assumed that the composition of the project’s steering committee would remain the same. But, since any change could be very critical to the project, the project manager assigned a team member to monitor potential triggers. Where should the name of the person responsible for monitoring the steering committee be documented?
Correct
A risk register contains a list of all identified risks, their description, planned responses, probability, impact, risk owner, etc. (PMBOK 7th edition, page 185). In the described scenario, the change in the composition of the steering committee is considered a risk and the name of the person responsible for managing it should be noted in the risk register. Once the risk occurs, it becomes an issue.
Incorrect
A risk register contains a list of all identified risks, their description, planned responses, probability, impact, risk owner, etc. (PMBOK 7th edition, page 185). In the described scenario, the change in the composition of the steering committee is considered a risk and the name of the person responsible for managing it should be noted in the risk register. Once the risk occurs, it becomes an issue.
-
Question 15 of 50
15. Question
The project sponsor informed the project manager that if the project costs exceed $350,000 by the end of the year, the project will receive no further funding. This is an example of which of the following?
Correct
A constraint is a limiting factor that restricts the options for managing a project, program, portfolio, or process. In this case, the following is a budget constraint that limits the project spending.
Option C: An issue is a present condition or situation that can potentially affect the project’s objectives.
Incorrect
A constraint is a limiting factor that restricts the options for managing a project, program, portfolio, or process. In this case, the following is a budget constraint that limits the project spending.
Option C: An issue is a present condition or situation that can potentially affect the project’s objectives.
-
Question 16 of 50
16. Question
The project team will hold a monthly status review meeting with the product owner to review post-iteration deliverables. What’s the best communication type to use in a status review meeting?
Correct
When an immediate response is required and the information you’re communicating is sensitive and could be misinterpreted, you should use interactive communication. It involves one or more people sharing thoughts and ideas, with participants responding in real time. Interactive communication can take place through teleconferences or face-to-face contact. When using communication media such as emails, the project manager can’t pick up on stakeholders’ facial expressions and body language.
Incorrect
When an immediate response is required and the information you’re communicating is sensitive and could be misinterpreted, you should use interactive communication. It involves one or more people sharing thoughts and ideas, with participants responding in real time. Interactive communication can take place through teleconferences or face-to-face contact. When using communication media such as emails, the project manager can’t pick up on stakeholders’ facial expressions and body language.
-
Question 17 of 50
17. Question
What is considered as an enterprise environmental factor?
Correct
Enterprise Environmental Factors (EEFs) refer to conditions, not under the control of the project team, that influence, constrain, or direct the project. These conditions could be internal or external to the organization. Organizational Culture is classified as an internal EEFs (PMI Process Groups, page 38).
Options A, C, D: Organization’s policies, lessons learned, and work performance data are organizational process assets, not Enterprise Environmental Factors.
Incorrect
Enterprise Environmental Factors (EEFs) refer to conditions, not under the control of the project team, that influence, constrain, or direct the project. These conditions could be internal or external to the organization. Organizational Culture is classified as an internal EEFs (PMI Process Groups, page 38).
Options A, C, D: Organization’s policies, lessons learned, and work performance data are organizational process assets, not Enterprise Environmental Factors.
-
Question 18 of 50
18. Question
What does this table represent?
Correct
Stakeholder Engagement Assessment Matrix is a matrix that shows stakeholder engagement levels.
Incorrect
Stakeholder Engagement Assessment Matrix is a matrix that shows stakeholder engagement levels.
-
Question 19 of 50
19. Question
On the graph below, what estimations correspond respectively to positions A, B, C, and D?
Correct
Accuracy describes how close a measurement is to an accepted value. Precision describes the statistical variability of produced measurement (it can be far off the accepted value) (PMBOK 7th edition, page 55).Incorrect
Accuracy describes how close a measurement is to an accepted value. Precision describes the statistical variability of produced measurement (it can be far off the accepted value) (PMBOK 7th edition, page 55). -
Question 20 of 50
20. Question
Industries, such as infrastructure, aerospace, and automotive, use ________________ for directional alignment and integration of component activities. The success of these initiatives is measured by the realization of intended benefits and the efficiency of delivering those benefits.
Correct
Many industries, such as infrastructure, aerospace, and automotive, use program management guides and frameworks. A program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. Programs are broader in scope and often focus on achieving long-term objectives (PMBOK 7, page 224).
Incorrect
Many industries, such as infrastructure, aerospace, and automotive, use program management guides and frameworks. A program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. Programs are broader in scope and often focus on achieving long-term objectives (PMBOK 7, page 224).
-
Question 21 of 50
21. Question
Which of the following best describes the “Project Life Cycle”?
Correct
The phases include initiation, planning, execution, monitoring, and closing, and they guide a project from inception to delivery and closure.
Incorrect
The phases include initiation, planning, execution, monitoring, and closing, and they guide a project from inception to delivery and closure.
-
Question 22 of 50
22. Question
Which of the following is NOT considered a characteristic of a high-performing project team?
Correct
High-performing teams prioritize collaboration, shared goals, and collective success rather than individual accomplishments.
Incorrect
High-performing teams prioritize collaboration, shared goals, and collective success rather than individual accomplishments.
-
Question 23 of 50
23. Question
How should a project manager promote resilience within the project team?
Correct
A resilient team is one that can adapt and recover from setbacks. Encouraging the team to learn from failures fosters a growth mindset and helps them to handle challenges with flexibility and perseverance.
Incorrect
A resilient team is one that can adapt and recover from setbacks. Encouraging the team to learn from failures fosters a growth mindset and helps them to handle challenges with flexibility and perseverance.
-
Question 24 of 50
24. Question
A project manager is conducting stakeholder analysis using the power/interest grid below. What actions correspond to the quadrants A, B, C, D respectively?
Correct
A. Keep Satisfied: Due to their influence, stakeholders with high power and low interest should be kept satisfied. But, because they don’t have a high interest in your project, they can get bored if you over-communicate with them.
B. Manage Closely: Stakeholders with high power and high interest are the most important to your project, and you should make sure to keep them happy by managing them closely.
C. Monitor: Stakeholders with low power and low interest should be kept informed periodically without overdoing it.
D. Keep Informed: You’ll want to keep stakeholders with low power and high interest informed by checking in with them regularly to make sure they are not experiencing any issues or problems.
Please note that in the real exam such a question usually comes in the form of “drag & drop”.
Incorrect
A. Keep Satisfied: Due to their influence, stakeholders with high power and low interest should be kept satisfied. But, because they don’t have a high interest in your project, they can get bored if you over-communicate with them.
B. Manage Closely: Stakeholders with high power and high interest are the most important to your project, and you should make sure to keep them happy by managing them closely.
C. Monitor: Stakeholders with low power and low interest should be kept informed periodically without overdoing it.
D. Keep Informed: You’ll want to keep stakeholders with low power and high interest informed by checking in with them regularly to make sure they are not experiencing any issues or problems.
Please note that in the real exam such a question usually comes in the form of “drag & drop”.
-
Question 25 of 50
25. Question
The person who is motivating and influencing the project team toward a common goal is best defined as a(n) ________ .
Correct
A leader’s primary role involves inspiring, motivating, and influencing team members to work towards a shared vision or common goal. Leadership focuses on people and their development, aiming to foster collaboration, build trust, and guide the team toward successful outcomes.
Incorrect
A leader’s primary role involves inspiring, motivating, and influencing team members to work towards a shared vision or common goal. Leadership focuses on people and their development, aiming to foster collaboration, build trust, and guide the team toward successful outcomes.
-
Question 26 of 50
26. Question
The project sponsor expressed concerns to the project manager about whether the resulting product will meet business needs. Therefore, the project sponsor is looking to keep costs to a minimum. What should the project manager do?
Correct
The Minimum Viable Product (MVP) is used to define the scope of the first release by identifying the requirements that would deliver value to customers (PMBOK 7th edition, page 243).
Incorrect
The Minimum Viable Product (MVP) is used to define the scope of the first release by identifying the requirements that would deliver value to customers (PMBOK 7th edition, page 243).
-
Question 27 of 50
27. Question
A project manager determines viable options and provides recommendations about the investment efficiency of two potential projects by implementing valuation techniques. Knowing that the discount rate is unknown, what should the project manager do?
Correct
Calculating a project’s Net Present Value (NPV) requires knowing its discount rate (i):
Net Present Value (NPV) = Future payment (F) / [ (1 + Discount rate (i) ) ^ number of periods in the future the cash flow is (n) ]. Since this is not an option in the described scenario, the project manager should rely on the Return On Investment (ROI) and pick the project with the highest value (The PMI Guide to Business Analysis, page 90).
Incorrect
Calculating a project’s Net Present Value (NPV) requires knowing its discount rate (i):
Net Present Value (NPV) = Future payment (F) / [ (1 + Discount rate (i) ) ^ number of periods in the future the cash flow is (n) ]. Since this is not an option in the described scenario, the project manager should rely on the Return On Investment (ROI) and pick the project with the highest value (The PMI Guide to Business Analysis, page 90).
-
Question 28 of 50
28. Question
An organization is considering two potential projects with identical payback periods. After conducting a benefit measurement analysis, the project manager discovers that project B has a higher Internal Rate of Return (IRR) than project A. Which project should the organization select?
Correct
The Internal Rate of Return is the annual rate of growth a project is expected to generate. The higher the IRR, the more desirable an investment is. Project B has a higher IRR, thus it will obviously be selected over Project A.
Incorrect
The Internal Rate of Return is the annual rate of growth a project is expected to generate. The higher the IRR, the more desirable an investment is. Project B has a higher IRR, thus it will obviously be selected over Project A.
-
Question 29 of 50
29. Question
The customer sends the project manager a document outlining the new project’s requirements. While checking the document, the project manager struggles to understand some of the requirements, outputs, and especially the ultimate goal of the project. What should the project manager do next?
Correct
In case of ambiguity, the project manager should first ask for clarifications from the customer before making any further decisions.
Option C: The project involves unclear requirements and objectives. Thus, it’s not appropriate to start planning project work or acquire a team without first creating a clear vision of what the project consists of.
Incorrect
In case of ambiguity, the project manager should first ask for clarifications from the customer before making any further decisions.
Option C: The project involves unclear requirements and objectives. Thus, it’s not appropriate to start planning project work or acquire a team without first creating a clear vision of what the project consists of.
-
Question 30 of 50
30. Question
To guide the development team on what they intend to achieve, a product owner provides a table that includes the key deliverables of each quarter of the 9-month project. What artifact does this table represent?
Correct
A product roadmap is a strategic plan that highlights the key components of a product that are scheduled for delivery across a portfolio, program, or several project iterations or releases, including the likely order in which these components will be delivered (The PMI Guide to Business Analysis, page 55). The product roadmap indicates where the product is headed in both the short and long terms. In agile organizations, the product roadmap serves as a guide rather than a project plan.
Incorrect
A product roadmap is a strategic plan that highlights the key components of a product that are scheduled for delivery across a portfolio, program, or several project iterations or releases, including the likely order in which these components will be delivered (The PMI Guide to Business Analysis, page 55). The product roadmap indicates where the product is headed in both the short and long terms. In agile organizations, the product roadmap serves as a guide rather than a project plan.
-
Question 31 of 50
31. Question
A business analyst is eager to implement a new solution for the company. The stakeholders requested an assessment of the business value it will bring. What should the business analyst do?
Correct
A cost-benefit analysis evaluates the financial return of implementing the solution by comparing the expected benefits against the costs. It’s an effective way to assess the business value of a solution.
Incorrect
A cost-benefit analysis evaluates the financial return of implementing the solution by comparing the expected benefits against the costs. It’s an effective way to assess the business value of a solution.
-
Question 32 of 50
32. Question
The project team finds out that several implemented features deviate from what is specified in the scope statement. Which document should the project manager consult to address the issue?
Correct
The traceability Matrix is a document that maps requirements as well as other aspects of the project. It’s used as evidence to confirm that requirements have been fulfilled, as it typically documents those requirements along with issues and test results (PMBOK 7th edition, page 189).
Incorrect
The traceability Matrix is a document that maps requirements as well as other aspects of the project. It’s used as evidence to confirm that requirements have been fulfilled, as it typically documents those requirements along with issues and test results (PMBOK 7th edition, page 189).
-
Question 33 of 50
33. Question
To validate requirements, a business analyst used a technique illustrated by the following graph. What technique did the business analyst use?
Correct
Delphi is a consensus-building method that consolidates anonymous input from subject matter experts (SMEs) using rounds of voting (The PMI Guide to Business Analysis, page 22
Incorrect
Delphi is a consensus-building method that consolidates anonymous input from subject matter experts (SMEs) using rounds of voting (The PMI Guide to Business Analysis, page 22
-
Question 34 of 50
34. Question
A project team is actively working on creating a solution and preparing it for delivery to the business. In which phase of the project would this activity take place?
Correct
In the Execution Phase, the project team develops, implements, and delivers the solution to the business. This phase involves carrying out the work defined in the project plan, managing resources, and ensuring that the deliverables meet the project’s objectives.
Incorrect
In the Execution Phase, the project team develops, implements, and delivers the solution to the business. This phase involves carrying out the work defined in the project plan, managing resources, and ensuring that the deliverables meet the project’s objectives.
-
Question 35 of 50
35. Question
An organization has appointed a new project manager to replace the one who recently left. What should the new project manager do first?
Correct
First and foremost, the project manager has to understand why the project is being created in the first place; aka its business case. Moreover, the project manager should be aware of the project’s predefined goals. These two elements along with the main deliverables are all defined in the project charter.
Incorrect
First and foremost, the project manager has to understand why the project is being created in the first place; aka its business case. Moreover, the project manager should be aware of the project’s predefined goals. These two elements along with the main deliverables are all defined in the project charter.
-
Question 36 of 50
36. Question
A Business Analyst is tasked with developing a product roadmap for the upcoming project. What technique should the Business Analyst choose to develop the roadmap in order to ensure it effectively captures the sequence and prioritization of user stories?
Correct
Story mapping is a technique for sequencing user stories based on their business value and the typical user sequence. It helps teams gain a shared understanding of the product to be built and communicates the features and components to be delivered. Initially, stories may be written at a high level as epics, which are later broken down into smaller stories.
Incorrect
Story mapping is a technique for sequencing user stories based on their business value and the typical user sequence. It helps teams gain a shared understanding of the product to be built and communicates the features and components to be delivered. Initially, stories may be written at a high level as epics, which are later broken down into smaller stories.
-
Question 37 of 50
37. Question
All stakeholders are attending a meeting to discuss a new project that is expected to start within a month and to last for at least 10 iterations. One stakeholder suggests that someone should be responsible for developing and maintaining the product roadmap. Who should assume this responsibility?
Correct
In agile, the product owner should be in charge of managing the product roadmap since they are responsible for the product’s success. The Product Owner’s primary responsibility is to represent the business, which involves the creation and maintenance of the Product Vision and Roadmap, as well as the Product Backlog.
Incorrect
In agile, the product owner should be in charge of managing the product roadmap since they are responsible for the product’s success. The Product Owner’s primary responsibility is to represent the business, which involves the creation and maintenance of the Product Vision and Roadmap, as well as the Product Backlog.
-
Question 38 of 50
38. Question
Which of the following elements are included in the business case? (Select three)
Correct
A situation statement is an objective summary of a problem or opportunity, explaining its effect on the organization and its impact. It is part of the business case and helps reviewers understand the challenge before evaluating potential solutions. It is the output of the “identify problem or opportunity” process.
Business goals and objectives define the specific outcomes a portfolio, program, or project is expected to achieve, they are the output of of the “determine future state” process and focus on targeted business outcomes Feasibility study results are the summarized findings from the feasibility analysis, compiled into a package to aid executive review and decision-making. Feasibility study results are the output of the process “determine viable options and provide recommendation”. (PMI Guide to Business Analysis, page 96)
Incorrect
A situation statement is an objective summary of a problem or opportunity, explaining its effect on the organization and its impact. It is part of the business case and helps reviewers understand the challenge before evaluating potential solutions. It is the output of the “identify problem or opportunity” process.
Business goals and objectives define the specific outcomes a portfolio, program, or project is expected to achieve, they are the output of of the “determine future state” process and focus on targeted business outcomes Feasibility study results are the summarized findings from the feasibility analysis, compiled into a package to aid executive review and decision-making. Feasibility study results are the output of the process “determine viable options and provide recommendation”. (PMI Guide to Business Analysis, page 96)
-
Question 39 of 50
39. Question
A new project manager has just been assigned to oversee a stopped project. To quickly get accustomed to the project’s processes and understand the scope of work, which tool would be the most effective?
Correct
A process flow visually outlines the steps or tasks involved in job functions or interactions with a product. It forms the foundation for training materials on new procedures and may include additional flows to detail the transition processes, helping the project manager understand what needs to be done.
Incorrect
A process flow visually outlines the steps or tasks involved in job functions or interactions with a product. It forms the foundation for training materials on new procedures and may include additional flows to detail the transition processes, helping the project manager understand what needs to be done.
-
Question 40 of 50
40. Question
Which of the following includes functional and non-functional requirements?
Correct
Solution requirements outline the specific attributes of a solution, including the features and functionalities of a product. These requirements address both business and stakeholder needs and must be detailed enough to guide the design and development of the solution effectively. Solution requirements have two subcategories: functional and non-functional requirements.
Incorrect
Solution requirements outline the specific attributes of a solution, including the features and functionalities of a product. These requirements address both business and stakeholder needs and must be detailed enough to guide the design and development of the solution effectively. Solution requirements have two subcategories: functional and non-functional requirements.
-
Question 41 of 50
41. Question
Which tool or technique is part of defining acceptance criteria?
Correct
Behavior-driven Development (BDD) involves defining acceptance criteria through a collaborative process, ensuring that conditions are clear and measurable through user stories and scenarios (PMI Guide to business analysis, pages 218 & 219).
Incorrect
Behavior-driven Development (BDD) involves defining acceptance criteria through a collaborative process, ensuring that conditions are clear and measurable through user stories and scenarios (PMI Guide to business analysis, pages 218 & 219).
-
Question 42 of 50
42. Question
A business analyst was assigned to an airline reservation system. The business analyst used the following artifact to illustrate the interactions with the system. What artifact did the business analyst use?
Correct
Use case diagrams are used to identify the list of both the users of the solution and the possible scenarios of how each user will use the solution (The PMI Guide to Business Analysis, page 206).
Incorrect
Use case diagrams are used to identify the list of both the users of the solution and the possible scenarios of how each user will use the solution (The PMI Guide to Business Analysis, page 206).
-
Question 43 of 50
43. Question
A retail has recently experienced a 20% drop in online sales. What is the first step a business analyst would take?
Correct
The business analyst needs to understand the current situation before determining the causes of the problem. Data collection allows for an evidence-based analysis of potential issues related to the user experience, website functionality, and customer trends, providing a foundation for future steps.
Incorrect
The business analyst needs to understand the current situation before determining the causes of the problem. Data collection allows for an evidence-based analysis of potential issues related to the user experience, website functionality, and customer trends, providing a foundation for future steps.
-
Question 44 of 50
44. Question
A product manager is pushing for the development of a new feature in an existing app. However, the business analyst has concerns that this feature may not address the core problem. What should the business analyst do next?
Correct
Pausing development and conducting a root cause analysis ensures that the business analyst properly investigates the underlying issue before moving forward with the solution.
Incorrect
Pausing development and conducting a root cause analysis ensures that the business analyst properly investigates the underlying issue before moving forward with the solution.
-
Question 45 of 50
45. Question
A business analyst collected product’s sales data and compared them to the business objectives. What process did the business conduct?
Correct
The business analyst is conducting the “Evaluate Solution Performance” process. This process is used to determine whether the implemented solution or solution component is delivering the business value as intended (The PMI Guide to Business Analysis, page 280).
Incorrect
The business analyst is conducting the “Evaluate Solution Performance” process. This process is used to determine whether the implemented solution or solution component is delivering the business value as intended (The PMI Guide to Business Analysis, page 280).
-
Question 46 of 50
46. Question
A business analyst is identifying the key problems and determining the necessary steps to move to a more efficient future state. Afterward, the business analyst will collaborate with stakeholders to ensure their concerns are addressed and obtain detailed information about their needs. These actions are part of which Business Analysis domains? (Select two)
Correct
Stakeholder engagement focuses on identifying stakeholders, understanding their needs, and engaging them throughout the project. Additionally, Needs assessment concentrates on identifying business problems or opportunities and determining the steps necessary to reach a future state.
Option B: Traceability and Monitoring is focused on ensuring that requirements and solutions are aligned throughout the project, tracing their status, and monitoring their progress. It does not involve identifying problems or engaging with stakeholders.
Option C: Although analysis involves examining data, processes, and models, it deals with creating and analyzing models and requirements, not with directly identifying problems or engaging stakeholders.
Option E: This area is focused on assessing how well the implemented solution meets the stakeholders’ needs and project objectives, which is something that occurs after the solution is developed, not during the initial phases of identifying problems or needs.
Incorrect
Stakeholder engagement focuses on identifying stakeholders, understanding their needs, and engaging them throughout the project. Additionally, Needs assessment concentrates on identifying business problems or opportunities and determining the steps necessary to reach a future state.
Option B: Traceability and Monitoring is focused on ensuring that requirements and solutions are aligned throughout the project, tracing their status, and monitoring their progress. It does not involve identifying problems or engaging with stakeholders.
Option C: Although analysis involves examining data, processes, and models, it deals with creating and analyzing models and requirements, not with directly identifying problems or engaging stakeholders.
Option E: This area is focused on assessing how well the implemented solution meets the stakeholders’ needs and project objectives, which is something that occurs after the solution is developed, not during the initial phases of identifying problems or needs.
-
Question 47 of 50
47. Question
Which elicitation technique should be used when seeking in-depth information from subject matter experts?
Correct
Interviews are the most appropriate elicitation technique when seeking in-depth information from subject matter experts. This approach allows for detailed, one-on-one discussions, enabling the business analyst to gather specific, expert insights that other techniques, like collaborative games or questionnaires, may not capture as effectively.
Incorrect
Interviews are the most appropriate elicitation technique when seeking in-depth information from subject matter experts. This approach allows for detailed, one-on-one discussions, enabling the business analyst to gather specific, expert insights that other techniques, like collaborative games or questionnaires, may not capture as effectively.
-
Question 48 of 50
48. Question
What skill enables a business analyst to leverage past experiences to make effective decisions when facing challenges?
Correct
Expert judgment involves using knowledge and expertise accumulated from prior projects and situations to make informed decisions, ensuring that solutions are aligned with both business goals and technical constraints.
Incorrect
Expert judgment involves using knowledge and expertise accumulated from prior projects and situations to make informed decisions, ensuring that solutions are aligned with both business goals and technical constraints.
-
Question 49 of 50
49. Question
Which of the following responsibilities is unique to business analysis?
Correct
Business analysis focuses on defining the product scope, which includes understanding business needs, gathering requirements, and ensuring the final product features and functions align with stakeholder expectations (PMI Guide to business analysis, page 17).
Incorrect
Business analysis focuses on defining the product scope, which includes understanding business needs, gathering requirements, and ensuring the final product features and functions align with stakeholder expectations (PMI Guide to business analysis, page 17).
-
Question 50 of 50
50. Question
A business analyst used the following model in analyzing product features from the viewpoint of the customer. What technique did the business analysis use?
Correct
The Kano model is an approach to prioritizing product functionalities based on their implementation cost versus their potential to satisfy customers
Incorrect
The Kano model is an approach to prioritizing product functionalities based on their implementation cost versus their potential to satisfy customers
Great work on completing Practice Test 1! To continue your progress:
- Return to the CAPM Practice Test main page and try Practice Test 2.
- Download our free CAPM Study Guide PDF for in‑depth explanations of all process groups.
CAPM Practice Test Syllabus
As mentioned earlier the Practice Test 1 comprises of Questions from Project Management Fundamentals & Core Concepts, and also on Business Analysis Frameworks. So, you have to face 25 Questions on Fundamentals and 25 qyestions related to Business Analysis.
Project Management Fundamentals & Core Concepts (25 questions)
- Definitions (e.g., project vs. operations, triple constraint)
- Key process groups and knowledge areas
- Stakeholder roles and responsibilities
- Integration, scope, schedule, cost, quality basics
Business Analysis Frameworks (25 questions)
- SWOT, PESTLE, MOST analyses
- Requirements elicitation techniques (e.g., interviews, workshops)
- Use case and user story development
- Traceability matrices and requirements management
Best Practices & Tips
- Read Carefully: Underline key phrases in the question stem to avoid misinterpretation.
- Eliminate First: Cross out obviously wrong answers to narrow your choices.
- Time Management: Aim for 1–1.2 minutes per question. If you’re stuck, flag it and move on.
- Scenario Focus: Many CAPM questions are situational. Think through the process flow before selecting your answer.
- Stay Calm: Trust your preparation—avoid second‑guessing unless you’re certain.